TxDOT to perform road maintenance this week; updates on projects

Jul 21, 2023

Multimedia Reporter

Multimedia reporter covering local government, Smith County and the City of Tyler with the Tyler Morning Telegraph. Texas native with a degree in Journalism and a minor in Women's and Gender Studies from UT-Arlington. Previously, reported on Limestone County with The Mexia News and The Groesbeck Journal.

TxDOT plans to conduct the following construction and maintenance work in the district during the week of Aug. 7. Work schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues.

TxDOT plans to conduct the following construction and maintenance work in the district during the week of Aug. 7. Work schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues.

Road crews will perform ditch maintenance in various locations throughout Smith County. People can expect lane closures with flaggers controlling traffic. A patching team will also be at multiple locations throughout the county.

Please slow down and pay attention in work zones.

SH 155 Resurfacing Project

Limits: From Loop 323 in Tyler, southwest to the Anderson County line

Contractor: Madden Contracting Company, LLC

Cost: $17 million

Anticipated Completion Date: Summer 2023

The contractor is scheduled to begin laying the PFC surface to the shoulders and turn lane at FM 2868. Expect delays and lane closures on this corridor when construction is in progress. Motorists should expect work during the day and night. The project will resurface the roadway, upgrade drainage structures, and repair bridge joints.

Tyler State Park Bridge and Resurfacing Project

Limits: Park Maintenance Road in Tyler State Park SW to Cedar Point Camping Area Exit

Contractor: Encino Landscape

Cost: $2.4 Million

Anticipated Completion Date: Summer 2023

The contractor is scheduled to continue the excavation of the retaining wall footing and establish the retaining wall grade and elevations. The project consists of bridge and pavement resurfacing.

Tyler State Park Rehabilitation Project

Limits: Park Maintenance roads, camp areas 5-8, additional parking in camp area 10, day-use parking area curb and gutter repair.

Contractor: East Texas Bridge, Inc.

Cost: $851,000

Anticipated Completion Date: Summer 2023

The contractor is scheduled to add topsoil, seeding, wheel stops and striping to finish off work at Milestone 5 (Maintenance Area) location. Park areas will be closed as operations are in progress. This project consists of rehabilitating parking areas at the camp sites and maintaining roadways.

I-20 Mill and Inlay

Limits: Van Zandt County Line to SH 110

Contractor: Texas Materials Group, INC.

Cost: $6 million

Anticipated Completion Date: Spring 2023

The contractor is scheduled to lay the PFC surface. Expect delays on this corridor when construction is in progress. The project consists of an overlay with TBPFC surface, ACP surface, planing, shoulder texturing and pavement markings.

SH 135 Bridge Replacements

Limits: Mud Creek Bridge and Mud Creek Relief Bridge

Contractor: Highway 19 Construction, LLC

Cost: $4.2 million

Anticipated Completion Date: Spring 2023

Though the contractor has completed all operations at the SH 135 Mud Creek & Mud Creek Relief bridge project site and the “Road is Open”, they will replace a damaged County Road sign to complete punch list repairs. This project consists of replacing the bridges at Mud Creek and Mud Creek Relief.

SH 64 Intersection Improvement and Turn Lanes

Limits: At CR 289 (Wolfe Lane)

Contractor: Lonestar Equipment Co. Inc.

Cost: $2.2 million

Anticipated Completion Date: Fall 2023

Weather permitting, the contractor is scheduled to place topsoil on the edge of the roadway and driveways. Expect delays on this corridor while construction is in progress. Lane closures are anticipated with the use of flaggers and a pilot car. The project consists of an intersection improvement and the addition of turn lanes at CR 289 (Wolfe Lane).

SH 110 in Whitehouse

Limits: Whitehouse

Contractor: Cross Plus Construction

Cost: $2.5 million

Anticipated Completion Date: August 2023

This project consists of installing sidewalks. Motorists should expect daily lane closures. Please slow down and watch for workers. Expect delays.

US 271 Rehab, Turn Lanes, and Pavement Overlay

· Limits: FM 16 SW to I-20

· Contractor: Madden Contracting Company, LLC

· Cost: $12.4 million

· Anticipated Completion Date: October 2023

The project includes paving, structures, MBGF and pavement markings from IH 20 N to the Gregg County Line. The portion from IH 20 to FM 16 includes turn lanes and pavement rehabilitation. The SB outside lane and shoulder are open. Additional lane closures are anticipated as crews work on adding other turn lanes, hot mixing the cross-overs and hot mixing side street intersections. Motorists should drive with caution and expect delays.

FM 16 Widening and Realignment

· Limits: 4 mi west of FM 849 east to US 69 in Lindale

· Contractor: Highway 19 Construction LLC.

· Cost: $44.4 million

· Anticipated Completion Date: August 2025

The project consists of grading, asphalt base, asphalt surface overlay paving, storm drain, bridge and culvert structures, signing, pavement markings and signals. Crews will be preparing the ROW by removing trees and grading embankments. Traffic shift detours are in place. Lane closures will be present in the area. Motorists should drive with caution and expect delays.

Multimedia Reporter

Multimedia reporter covering local government, Smith County and the City of Tyler with the Tyler Morning Telegraph. Texas native with a degree in Journalism and a minor in Women's and Gender Studies from UT-Arlington. Previously, reported on Limestone County with The Mexia News and The Groesbeck Journal.

“This is what the Lord says, he who made the earth, the Lord who formed it and established it — the Lord is his name: ‘Call to me and I will answer you and tell you great and unsearchable things you do not know.’" (Jeremiah 33:2-3)

Smith County construction projects updates:SH 155 Resurfacing ProjectTyler State Park Bridge and Resurfacing ProjectTyler State Park Rehabilitation ProjectI-20 Mill and InlaySH 135 Bridge ReplacementsSH 64 Intersection Improvement and Turn LanesSH 110 in WhitehouseUS 271 Rehab, Turn Lanes, and Pavement OverlayFM 16 Widening and Realignment